On the 10th. March 2005, Wet
Process Bore Pilling Works was commenced
- Diameter
500mm of 116 Nos. Bored Pills
- Diameter
600mm of 111 Nos. Bored Pills
Average
penetration depth of 19.5 Meters
underground.
Super-structural Works commencing from
18th. May 2005
The
following Works were commenced in
December 2005
- Architectural: Floor Tiling, Bricks
Wall Partition, Gypsum Board Ceiling,
Plastering, & Painting, Aluminum Roller
Shutter Doors, Glass Doors and Windows
- Mechanical: Lifts, Escalators,
Ventilation and Air-conditioning System
Electrical:
Transformers, MSB, DBs, LV Switches,
Wiring, Lightings, Lightning Protection,
P.A. Sound System, and CCTV System.
- Water,
Plumbing, Sanitary, Fire Hose reel, Fire
Alarm System
Water
Ponding Test for Roof Top
Leakage/Penetration Prevention, Megger
Test for Electrical Installation and
Lifts Loading Test for Safety Operation
of all Lifts & Escalators were conducted
and Passed, Inspection by Local
Authorities with Approval given before
opening.
The
Building was completed and opening for
Public on 6th. April 2007.
|